Client & System Integrator: Tanglian Chem (Tanglian Equipment Co., Ltd.)
Industry: Chemical Industry
Facility Location: Evaporation & Crystallization Project Site
Equipment Scope: Thin-Film Evaporators, Rectification Column Assembly, Multi-Tier Steel Structure Platform, Condensers, Vacuum Systems, Process Valves, and Piping Infrastructure
Project Outcome: The team completed all installation and commissioning work. As a result, Tanglian Chem handed over the operational plant to the client.

1. Project Overview and Plant Design
Tanglian Chem completed a major chemical equipment installation project. Specifically, our team built a multi-story steel platform at the site. Next, we installed thin-film evaporators and a tall rectification column. Finally, we connected the full process piping network.
=====================================================================================
EVAPORATION & CRYSTALLIZATION PLANT: INTEGRATED SYSTEM ARCHITECTURE
=====================================================================================
+---------------------------------------------------------------------------------+
| MULTI-TIER STEEL STRUCTURE PLATFORM |
| |
| +---------------------------------------------------------------------------+ |
| | UPPER LEVEL: RECTIFICATION & CONDENSATION | |
| | | |
| | [Rectification Column Top] ===> [Overhead Condensers & Reflux System] | |
| +---------------------------------------------------------------------------+ |
| | |
| v |
| +---------------------------------------------------------------------------+ |
| | MIDDLE LEVEL: THIN-FILM EVAPORATION DECK | |
| | | |
| | [Thin-Film Evaporators] <===> [Vapor-Liquid Separators] | |
| +---------------------------------------------------------------------------+ |
| | |
| v |
| +---------------------------------------------------------------------------+ |
| | GROUND LEVEL: CRYSTALLIZATION & PUMPING ZONE | |
| | | |
| | [Product Discharge Pumps] <===> [Process Utility Pipes] | |
| +---------------------------------------------------------------------------+ |
| |
+---------------------------------------------------------------------------------+
=====================================================================================
Evaporation and crystallization systems process complex liquid mixtures. In addition, these systems recover solid materials and clean wastewater. Therefore, the equipment must handle heat, liquid flow, and deep vacuum pressures without leaking.
For this project, Tanglian Chem mounted all main machinery onto a shared steel framework. Consequently, liquid flows efficiently between processing levels. In fact, our field crew completed every phase safely and on schedule.
2. Structural Steel Platform Erection
First, the team built a multi-tier steel structure platform. This platform supports heavy evaporators, tall columns, and overhead pipes.
[Steel Structure Platform Erection Sequence]
+-----------------------------------------------------------------+
| Step 1: Secure Heavy Base Columns into Concrete Foundation |
+--------------------------------+--------------------------------+
|
v
+--------------------------------+--------------------------------+
| Step 2: Assemble Load-Bearing Crossbeams & Floor Gratings |
+--------------------------------+--------------------------------+
|
v
+-----------------------------------------------------------------+
| Step 3: Apply Protective Primer & Chemical-Resistant Topcoat |
+-----------------------------------------------------------------+
Framework Assembly and Mounting
First, workers assembled heavy steel columns and floor beams. Consequently, the frame easily supports dynamic machinery loads. Next, installers laid non-slip steel floor gratings across all walkways. Therefore, operators can safely inspect equipment at every level.
Surface Protection and Anchoring
Furthermore, painters coated all steel members with an epoxy primer. Next, they applied a tough polyurethane topcoat. As a result, the steel frame resists chemical spills and weather damage. Finally, technicians anchored the column bases into concrete pads using heavy steel studs.
3. Thin-Film Evaporator Installation
Next, crews hoisted the thin-film evaporators onto the middle platform level. These machines spread liquids into thin layers along heated interior walls.
[Thin-Film Evaporator Components]
[Top Drive Motor & Gearbox]
|
+-----------------+-----------------+
| Upper Mechanical Shaft Seal |
+-----------------+-----------------+
|
+-----------------+-----------------+
| Heated Main Shell & Scraper Rotor |
+-----------------+-----------------+
|
+-----------------+-----------------+
| Bottom Discharge Cone Outlet |
+-----------------------------------+
Positioning and Alignment
First, riggers lifted the evaporator bodies using mobile cranes. Meanwhile, spotters guided each unit onto its mounting beams. Next, technicians checked horizontal levelness using digital optical tools. Therefore, installers placed steel shims under support pads to achieve perfect balance.
Drive Shaft Assembly
In addition, mechanics installed top drive motors and internal rotor shafts. Next, workers adjusted the drive couplings. As a result, the internal wiper blades rotate smoothly inside the heated shell without touching the walls. Finally, mechanics attached coolant lines to the mechanical shaft seals.
4. Rectification Column Rigging and Vertical Alignment
After setting the evaporators, the team raised the tall rectification column. This column separates liquids using heat and vapor pressure.
[Primary Mobile Crane]
|
+----------+----------+
| Main Spreader Beam |
+----+-----------+----+
| |
+--------+ +--------+
| |
v v
+-----------+ +-----------+
| Column | | Column | (Dual-Crane Lifting)
| Top Head | | Base Tail |
+-----+-----+ +-----+-----+
| |
===============================================
| Rectification Column Body Shell |
===============================================
Dual-Crane Lifting Strategy
First, riggers planned a dual-crane lift to raise the column sections. Specifically, a large crane lifted the top section. Meanwhile, a smaller crane guided the bottom tail. Consequently, the team raised the long column safely without bending the metal shell.
Laser Alignment and Packing
Next, workers bolted the column sections together using chemical gaskets. In addition, surveyors placed laser tools on perpendicular ground points. Consequently, installers checked vertical straightness along the entire height. Finally, workers loaded high-efficiency packing grids inside the column through access ports.
5. Process Piping, Valves, and Vacuum Systems
After fixing all primary machinery, pipefitters connected the full piping network. This network carries liquid feeds, steam, vapors, and clean discharge.
+------------------------+ +------------------------+ +------------------------+
| 1. Pipe Spool Welding | --> | 2. Valve Integration | --> | 3. Vacuum Line Tie-In |
+------------------------+ +------------------------+ +------------------------+
| - Weld 316L pipe lines | | - Install auto valves | | - Connect ejectors |
| - Inspect inner beads | | - Set pressure sensors | | - Mount condensers |
| - Fit connection joints| | - Wire control loops | | - Seal all pipe joints |
+------------------------+ +------------------------+ +------------------------+
Piping Fabrication and Fitting
First, certified welders fabricated stainless steel pipes for process liquids. Furthermore, workers inspected all weld seams to ensure smooth interior surfaces. As a result, liquids flow freely through the system without clogging.
Valves and Utility Integration
Next, installers mounted control valves, safety valves, and temperature sensors. Meanwhile, electricians ran signal cables from sensors back to the main control room. Finally, technicians connected steam supply lines to heating jackets and reboilers.
Vacuum System Connection
In addition, workers installed overhead condensers and steam jet vacuum pumps. Consequently, these components create the low pressure needed for low-temperature separation.
6. System Pressure Testing and Dynamic Commissioning
Before starting actual production, Tanglian Chem ran full safety and operational tests.
+------------------------+ +------------------------+ +------------------------+
| 1. Water Pressure Test | --> | 2. Vacuum Hold Test | --> | 3. Dynamic Water Run |
+------------------------+ +------------------------+ +------------------------+
| - Fill jackets & pipes | | - Evacuate all vessels | | - Run motor drives |
| - Pressurize system | | - Hold vacuum 24 hours | | - Feed clean water |
| - Check for leaks | | - Verify airtight seals| | - Check temperature |
+------------------------+ +------------------------+ +------------------------+
Water Pressure and Vacuum Tests
First, technicians filled heating jackets and pipes with water. Next, they pressurized the lines to check for joint leaks. As a result, all pipe connections proved completely watertight.
Furthermore, the team pulled a deep vacuum across the entire plant. Then, workers held the vacuum for 24 hours. Consequently, digital gauges showed steady pressure readings, proving the system is airtight.
Dynamic Water Trials
Finally, operators ran dynamic trial runs using clean water. Specifically, technicians started the thin-film evaporator motors and checked shaft vibration. Next, workers introduced steam to heat the system. As a result, liquid boiled, evaporated, condensed, and discharged smoothly through the plant.
7. Performance Results Summary
The table below shows key performance targets and actual site test results.
| Inspection Item | Target Standard | Actual Site Result | Status |
|---|---|---|---|
| Platform Framework | Full load rating compliance | Passed civil load inspection | Passed |
| Column Straightness | Perfectly vertical alignment | Straight within target limits | Passed |
| Evaporator Levelness | Balanced horizontal level | Level within target limits | Passed |
| Evaporator Shaft Play | Smooth spinning movement | Deviation within safe limits | Passed |
| Pipe Weld Quality | Full weld joint strength | Passed 100% visual checks | Passed |
| 24-Hour Vacuum Hold | Zero pressure loss over time | Held steady vacuum pressure | Passed |
| Control Signal Feedback | Accurate sensor readings | Passed signal loop audits | Passed |
| Motor Drive Vibration | Low motor vibration levels | Smooth running values | Passed |
Tanglian Chem completed all platform construction, equipment rigging, piping connection, pressure testing, and trial runs on time. Therefore, the evaporation and crystallization line passed all client acceptance audits. As a result, the plant is fully ready for commercial chemical production.