Client & System Integrator: Tanglian Chem (Tanglian Equipment Co., Ltd.)
Industry: New Energy & Advanced Energy Storage Technology
Facility Location: Energy Research & Development Experimental Base
Equipment Scope: Double-Tier White Steel Structure Framework, Upper Stainless Steel Reactor with Blue Drive Motor, Grey Pressure Storage Tank, Lower Suspended Stainless Steel Vessel, Right-Side Electrical Control Cabinet, and Integrated Process Piping
1. Executive Project Overview and Facility Architecture
Tanglian Chem completed the mechanical assembly, structural erection, process piping, electrical wiring, and joint system commissioning for a pilot-scale reaction unit. Specifically, our engineering team installed this integrated system inside the principal experimental bay at the Energy Research & Development Experimental Base.
Plaintext
=====================================================================================
NEW ENERGY EXPERIMENTAL BASE: PILOT REACTION SYSTEM ARCHITECTURE
=====================================================================================
+-------------------------------------------------------------------------------+
| UPPER TIER (Platform Elev. +3.2m) |
| |
| +--------------------------+ +----------------------------+ |
| | Stainless Steel Reactor | | Grey Pressure Storage Tank | |
| | [Blue Agitation Motor] | | (Welded Support Hangers) | |
| +------------+-------------+ +-------------+--------------+ |
| | | |
+----------------|-------------------------------------|------------------------+
| |
+----------------|-------------------------------------|------------------------+
| LOWER TIER (Ground Elev. +0.0m) | |
| v v |
| +--------------------------+ +----------------------------+ |
| | Suspended Stainless Tank | | Right-Side Control Cabinet | |
| | [Bottom Discharge Valve] | | [PLC / VFD / HMI Touch] | |
| +--------------------------+ +----------------------------+ |
| |
| ==> White Structural Frame | Yellow Safety Guardrails & Access Ladder <== |
+-------------------------------------------------------------------------------+
=====================================================================================
The pilot plant accelerates the development of next-generation energy storage chemicals, battery precursor slurry formulations, and synthetic clean fuels. To maximize vertical room space while providing ergonomic operator access, engineers designed a modular, two-tier vertical footprint.
Ultimately, Tanglian Chem delivered a fully operational processing unit. The double-layer steel platform passed structural acceptance on the first inspection. Furthermore, all static and dynamic equipment operated within design parameters during joint electrical-mechanical trial runs, enabling immediate turnkey handover to the client’s research staff.

hw-remosaic: false;
touch: (-1.0, -1.0);
modeInfo: HDR ;
sceneMode: 2;
cct_value: 5656;
AI_Scene: (-1, -1);
aec_lux: 227.0;
aec_lux_index: 0;
hist255: 0.0;
hist252~255: 0.0;
hist0~15: 0.0;
motionLevel: -1;
weatherinfo: null;

hw-remosaic: false;
touch: (-1.0, -1.0);
modeInfo: ;
sceneMode: 2;
cct_value: 6031;
AI_Scene: (-1, -1);
aec_lux: 226.0;
aec_lux_index: 0;
hist255: 0.0;
hist252~255: 0.0;
hist0~15: 0.0;
motionLevel: -1;
weatherinfo: null;
2. Phase I: Double-Layer White Steel Structural Framework & Safety Infrastructure
The structural foundation of the test rig consists of a heavy-duty, two-tier steel framework. Because research environments require high cleanliness and clear visual inspection, engineers specified a clean white protective coating for the primary skeleton, paired with high-visibility signal yellow for all safety barriers.
Plaintext
[Upper Floor Framing]
| |
+----+-------------+----+
| Main I-Beam (White) | <--- High-Gloss Anti-Corrosion Polyurethane
+----+-------------+----+
| |
v v
+-----------------------+
| Vertical Column (3.2m)| <--- Anchor Baseplate to Concrete Foundation
+-----------------------+
Framework Design and Fabrication
First, fabricators built the main vertical columns and floor girders from Q355B structural steel profiles. The shop team applied a multi-stage coating process consisting of an epoxy zinc-rich primer followed by a high-gloss aliphatic polyurethane topcoat in pure white. This smooth white finish reflects ambient light, resists chemical splashes, and allows laboratory technicians to spot leaks instantly.
Safety Barrier and Access Construction
Next, installation crews mounted anti-slip galvanized diamond plate decking across the second-tier operating platform. Subsequently, mechanics erected safety barriers around the perimeter:
- Yellow Safety Guardrails: Installers welded continuous 1100mm high handrails with mid-rails and 150mm toe-boards along all open edges. Painters coated these barriers in safety yellow (RAL 1023) for maximum visibility.
- Access Cage Ladder: In addition, technicians secured a vertical steel access ladder with a protective safety cage, connecting the ground floor to the upper platform.
Plaintext
[Guardrail Profile]
+--------------------------+ <-- Top Handrail (1100 mm Height, Safety Yellow)
| |
+--------------------------+ <-- Mid-Rail (550 mm Height)
| |
---------------------------- <-- Toe-Board (150 mm Height)
============================ <-- Diamond Plate Platform Decking
Structural Anchoring and Acceptance
Finally, field engineers anchored the column baseplates into the reinforced concrete slab using heavy-duty chemical wedge anchors. Dynamic load calculations verified that the structure handles both static equipment weights and rotational torque generated by the agitator motor. Consequently, civil safety inspectors formally signed off on the double-layer platform framework.
3. Phase II: Upper & Lower Vessel Rigging, Leveling, and Mechanical Assembly
The core process unit houses three distinct vessels positioned across both tiers: an upper stainless steel reactor, a supporting grey pressure tank, and a lower suspended receiver vessel.
Plaintext
[Blue Drive Motor & Gearbox]
|
+---------+---------+
| Upper SS Reactor | <-- Tier 2 Operating Level
+---------+---------+
|
v
[Process Transfer Line]
|
v
+---------+---------+
| Suspended Tank | <-- Tier 1 Ground Level
+---------+---------+
|
[Bottom Discharge Valve]
Upper-Layer Stainless Steel Reactor Installation
First, riggers used an indoor mobile gantry crane and synthetic slings to hoist the stainless steel reaction kettle onto the Tier 2 platform.
- Precision Alignment: Next, surveyors used a digital optical level to measure horizontal tolerances across the upper vessel flange. Technicians inserted precision stainless steel shims under the mounting lugs until achieving a levelness of ≤0.2mm/m.
- Agitation Drive Integration: Subsequently, mechanics mounted the heavy-duty drive assembly—featuring a distinctive blue explosion-proof motor and speed reducer—onto the top head. Engineers measured agitator shaft runout using a magnetic dial indicator, keeping total radial deviation within ≤0.04mm.
Supporting Grey Pressure Storage Tank Mounting
Concurrently, the rigging crew hoisted the secondary pressure storage tank, finished in industrial grey polyurethane, onto the upper tier.
- Hanger Welding: Welders joined heavy-duty pipe supports and structural sway braces directly to the white steel girders.
- Non-Destructive Testing: To ensure structural safety under pressurized conditions, inspectors performed dye-penetrant testing (PT) on all load-bearing hanger welds, confirming zero surface defects.
Lower-Layer Suspended Stainless Steel Vessel & Valve Assembly
Meanwhile, technicians installed a stainless steel receiver vessel suspended directly beneath the Tier 2 platform floor.
- Suspension Anchoring: Installers secured the vessel using threaded rod hangers and rubber isolation bushings to dampen fluid movement.
- Drain Valve Assembly: Finally, mechanics fitted a zero-dead-leg flush bottom discharge valve to the lower tank outlet. This valve prevents product stagnation and ensures complete batch drainage during experimental runs.
4. Phase III: Piping, Instrumentation, and Electrical Control Integration
Following mechanical positioning, technicians routed all process utility lines and wired the main electrical control system on the right side of the rig.
Plaintext
[Sensors / Transmitters] [Blue Motor / Valves]
| |
+--------------+---------------+
|
v (Shielded Cable Trays)
+------------------------------+
| Right-Side Control Cabinet |
| +------------------------+ |
| | PLC / VFD / HMI Panel | |
| +------------------------+ |
+------------------------------+
Process Piping and Valve Installation
First, pipefitters installed electro-polished stainless steel lines connecting the upper reactor, grey pressure tank, and lower receiver vessel.
- Valves & Gauges: Installers mounted manual isolation ball valves, pneumatic control valves, local dial pressure gauges, and sanitary thermowells.
- Utility Connections: In addition, crews connected flexible stainless hoses for heating/cooling jacket fluid and inert nitrogen gas purging.
Right-Side Electrical Control Cabinet & Wiring
To maintain ergonomic operation, electricians installed the primary control cabinet on the ground floor along the right side of the steel frame.
Plaintext
[Control Cabinet Front Panel]
+-----------------------------------+
| [ Main Power Switch ] |
| [ Emergency Stop Button ] |
| |
| +-----------------------------+ |
| | HMI Touchscreen Display | |
| | - Agitator Speed (RPM) | |
| | - Temp & Pressure Readouts | |
| +-----------------------------+ |
| |
| [ VFD Run ] [ Heating Control ] |
+-----------------------------------+
- Cabinet Fitting: Electricians floor-mounted an IP65 powder-coated enclosure housing the Programmable Logic Controller (PLC), Variable Frequency Drive (VFD), power supplies, and circuit breakers.
- Cable Routing: Installers laid power cables (380V 3Φ) and signal wiring (4–20mA HART / RS485) inside separate metallic conduit channels. This separation prevents electromagnetic interference from the VFD from degrading sensitive sensor readings.
- Agitator Wiring: Finally, technicians wired the blue motor to the cabinet output terminals, complete with an external emergency stop button mounted on the upper platform rail.
5. Joint Commissioning, System Testing, and Performance Results
To prepare for final handover, Tanglian Chem performed a systematic sequence of dry runs, wet trials, and electrical loop checks.
Plaintext
+--------------------+ +--------------------+ +--------------------+
| 1. Cold Loop Check| --> | 2. Pressure Test | --> | 3. Dynamic Run |
+--------------------+ +--------------------+ +--------------------+
| - Wire continuity | | - Nitrogen hold | | - Agitator speed |
| - Sensor 4-20mA | | - Leak spray verification| - Temp control loop|
| - Valve feedback | | - Gauge matching | | - Discharge flow |
+--------------------+ +--------------------+ +--------------------+
Commissioning Steps
- Cold Loop Verification: First, control engineers verified point-to-point wiring continuity, HMI signal feedback, and valve open/close response times.
- Pressure Integrity Hold Test: Next, technicians pressurized the grey storage tank and upper reactor jacket with nitrogen gas to 1.1× operating pressure, holding the charge for 6 hours with zero detectable pressure drop.
- Dynamic Water Trial: Finally, operators charged the reactor with deionized water. The team energized the blue agitator motor, ramping speed from 0 to 400RPM in 50RPM increments. The lower discharge valve opened smoothly under auto-control, draining the batch completely.
6. Project Results Summary Matrix
The following table summarizes the verified operational parameters recorded during final acceptance testing.
| Evaluation Parameter | Design Specification Target | Actual Commissioning Result | Status |
|---|---|---|---|
| Platform Frame Acceptance | Structural code compliance | 100% passed civil inspection | Passed |
| Upper Reactor Levelness | ≤0.5mm/m horizontal tilt | 0.12mm/m measured | Passed |
| Agitator Shaft Runout | ≤0.05mm total radial play | 0.028mm measured | Passed |
| Motor Vibration (Max RPM) | ≤1.8mm/s RMS | 0.85mm/s RMS recorded | Passed |
| Pressure Hold Integrity | 6-hour hold at test pressure | 0.00bar pressure drop | Passed |
| Control Signal Accuracy | ≤±0.2% full scale loop error | ≤±0.05% error measured | Passed |
| Bottom Valve Seal Integrity | Bubble-tight zero liquid leakage | Zero drip leak at full head pressure | Passed |
| Noise Level (at 1 Meter) | ≤70.0dBA at full load | 63.2dBA recorded | Passed |
7. Project Summary
In conclusion, Tanglian Chem completed the mechanical positioning, structural erection, piping integration, and electrical installation for the new energy pilot plant. The white steel structure, yellow safety guardrails, stainless steel reactors, grey pressure vessel, and right-side electrical cabinet function together as a unified system.
By passing all static inspections and dynamic joint commissioning runs on the first attempt, the reaction unit reached complete operational readiness. The system was delivered directly into live research service, providing the client with a reliable platform for advanced energy technology experimentation.